Peter Matthews Drive Bridges

Peter Matthews Drive Bridges under construction in Pickering

Two bridge structures on the Peter Matthews Drive reconstruction in Pickering: the main crossing under the hydro corridor and the bridge carrying the road over the CP Rail corridor. Scope across both included foundations, abutments and wingwalls, bearings for prestressed girders, deck placement, parapet and barrier walls, expansion joints, sleeper and approach slabs, and the reinforced soil slope retaining wall at the rail crossing.

Project Details
TypeTwo New Bridge Structures
StructureCast-in-Place Concrete
LocationPickering, ON
StatusComplete
Year2020-2026